Project Status


Home
Site Photographs


Chuck Vreeland

FDOT Project Manager

Project Team

Ardaman and Associates, Inc

Jones Wood And Gentry Inc

 

 

PROJECT STATUS

August 20, 2003


·     The PD&E phase of the project is nearly complete.  The following are the completion dates or expected completion dates of several major PD&E milestones:

 -        PD&E Public Workshop                                                            October 15, 2002

-        PD&E Public Hearing                                                                May 13, 2003

-        Categorical Exclusion Approval by FHWA                           August  12, 2003

-        PD&E plans reviewed by FDOT                                              June, 2003

-        FDOT approval of the typical section                                     Expected by August 28, 2003

-        Complete final responses to public comments                     Expected by September 12, 2003

-        Alt. Selection notification letter to agencies                           Expected by August 25, 2003

-        Final signed and sealed PD&E plan submittal                     Expected by September 30, 2003

-        Location, Design and Concept Acceptance by FHWA        Expected by September 30, 2003

 

·     The Preliminary design and Design/Build criteria package development phase is just beginning.  The following are key dates for this phase of work:

-        Design kickoff                                                                                 July 7, 2003

-        Typical section package complete by                                         September 30, 2003

-        Pavement design package complete by                                     November 15, 2003

-        Complete field survey and geotechnical work by                    December 16, 2003

-        Submit initial preliminary plans to FDOT                                 January 30, 2004       

-        Submit completed preliminary plans to FDOT                         March 26, 2004

-        Hold design phase public meeting                                              March 29, 2004

-        Submit right-of-way requirements to FDOT                               May 31, 2004

-        Complete final design/build RFP and design criteria pkg.    September 17, 2004

 

·         Right-of-way maps complete                                                        January 24, 2005

·         Right-of-way certified                                                                    January 8, 2007

·         Design/Build team contract signed                                            February 1, 2007

 


 

Home | Project Objectives | Project Status | Project Location | Public Involvement | Contact Information

 
Copyright 2003 by CH2M HILL. Reproduction in whole or in part without the written consent of CH2M HILL is prohibited

For problems or questions regarding this Web site contact Webmaster.

Last updated: 08/21/03.