Colorado Springs Submits Permit to Fremont
County
A Special Review Use Permit application was submitted to Fremont
County on Sept. 10 for the Southern Delivery System project. The
permit outlines Fremont County’s requirements as it relates
to construction, technical issues and mitigation of impacts for
projects built in their county.
While our preferred alignment for SDS is a 43-mile
underground pipeline originating at Pueblo Dam, Colorado Springs
is concurrently pursuing a viable alternative in Fremont County.
“It is our preference to use the valuable storage capacity
of Pueblo Reservoir, since our residents have made significant investments
in that facility,” said John Fredell, SDS Project Director.
“A pipeline from Pueblo Dam is the most direct and least expensive
alternative for our customers. However, we also want to have the
proper permitting in place for the Highway 115 Alternative in Fremont
County.”
The Highway
115 Alternative is a pipeline through Fremont County with an
intake on the Arkansas River in Florence. One of the key goals of
the SDS project is to ensure that the required permitting is in
place once the Bureau of Reclamation issues its Record of Decision
based on the Environmental
Impact Statement it is preparing for the project.
"It is in the best interest of our customers that we complete
permitting for both Pueblo and Fremont counties at this time,"
said Fredell.
Colorado Springs submitted a 1041 land-use permit application to
Pueblo County on Aug. 20.
|