Project Description

Proposed Action

Our Preferred Alternative for SDS is a 53-mile-long underground pipeline originating from Pueblo Dam. It also includes one pump station in Pueblo County, plus two pump stations, a water-treatment plant and two reservoirs in El Paso County.

A pipeline from Pueblo Dam is the most cost effective and efficient option among the hundreds of possible combinations considered because it:

There are significant operational efficiencies with taking our water directly from Pueblo Reservoir.
Lower construction costs than other options.
Will increase our overall system reliability in the event other parts of our system need maintenance or repair.

Permitting information for Preferred Alternative