Permitting - Pueblo County

Pueblo County 1041 Land-Use Permit

The Pueblo Board of County Commissioners unanimously approved a resolution on April 21, 2009, to issue a 1041 land-use permit for the Southern Delivery System Preferred Alternative. The approval followed a Colorado Springs City Council vote in favor of a resolution to formally recognize the commitments in the terms and conditions of the Pueblo County 1041 land-use permit on April 14, 2009.

The permit identifies construction and environmental mitigation required to build the SDS permit through Pueblo County as well as outlining how the approach to acquiring property for the project. Following is a high level summary of the conditions included in the 1041 Permit. Colorado Springs, acting in the capacity of project manager for SDS, will be required to:

Mitigation of Fountain Creek Impacts
Mitigate impacts to Fountain Creek from SDS by funding $50 million to the new Fountain Creek Watershed, Flood Control and Greenway District (District) or similar entity for erosion, sedimentation, flood control or water quality improvement projects.
Payments would be made in five annual installments after water begins flowing through the SDS pipeline.
Of that total, Colorado Springs would pay $300,000 in equal annual installments of $100,000 each beginning July 1, 2009, to assist in the identification and prioritization of projects, and to fund a study or studies of opportunities for constructing flood control and sediment control facilities which may include the feasibility of a dam or dams on Fountain Creek or its tributaries in order to improve flood protection for the Fountain Creek Basin.
Colorado Springs Utilities to invest $75 million in planned improvements to its wastewater collection system or reuse systems by Dec. 31, 2024 to protect against future spills, increase its opportunities for reuse, and mitigate possible water quality impacts from SDS.
Reduce sediment load in lower Fountain Creek prior to SDS construction by dredging and sediment-collection.

Stormwater Management
Maintain stormwater controls and other regulations intended to ensure that Fountain Creek peak flows resulting from new development served by the SDS project within the Fountain Creek basin are no greater than existing conditions. This requirement can only apply to Project Participants who have the legal authority to regulate in this manner.

Protection of the Arkansas River/Pueblo Reservoir
SDS participants would continue participation in the Pueblo Flow Management Program to protect Arkansas River flows below Pueblo Dam for recreation and the Arkansas River Corridor Legacy Project.
Colorado Springs Utilities to work with the Pueblo Board of Water Works to outline how the two cities will maintain a storage pool in Pueblo Reservoir to permit the release of water into the Arkansas River during times when the flow in the river could fall to dangerously low levels – at or below 50 cubic feet per second (cfs).
Wait to begin construction at or near Pueblo Reservoir Dam until after the Bureau of Reclamation performs its dam-safety review and accepts the design construction plans.
Colorado Springs Utilities would voluntarily participate in developing a management plan for Pueblo Reservoir to protect reservoir levels and recreational opportunities on Pueblo Reservoir to the extent feasible, when and if the Southeastern Colorado Water Conservancy District, Reclamation and other affected parties agree to develop such a plan.

Other Water Users
Colorado Springs could elect to add SDS project participants if the entities are located in El Paso and Teller Counties within the Arkansas River Basin and agree to meet criteria outlined in the conditions.

Property Owners/Construction
Treat private property owners fairly, avoid creating financial burdens for property owners, and use power of eminent domain “only as a last resort” to acquire property and easements.
Mitigate construction impacts and restore disturbed lands.
Take “substantial steps” within 36 months to “construct the permitted development.”

Details of the Pueblo County 1041 Permit Conditions
Final resolution approving the permit. [Link to resolution]
Terms and conditions. PDF (47 KB)
Permit Mitigation Appendix. PDF (438KB)
MOU Arkansas River Low Flow Program. PDF (421KB)
MOU Delivery of Municipal Water Supplies from Pueblo Reservoir. PDF (734KB)

Articles and Presentations
SDS Factsheet. PDF Document.
April 22, 2009 – Pueblo County approves Utilities secures key permit for SDS. Pueblo Chieftain article on 1041 permit approval. PDF Document.
April 21, 2009 – Utilities secures key permit for Southern Delivery System. Gazette article on 1041 permit approval. PDF Document.
April 9, 2009 – Presentation Colorado Springs City Council on 1041 Permit conditions. PDF Document.
December 9, 2008 – Presentation to Pueblo County Commission on 1041 Permit application. PDF Document.