Pueblo County 1041 Land-Use Permit
The Pueblo Board of County Commissioners unanimously approved a
resolution on April 21, 2009, to issue a 1041 land-use permit for
the Southern Delivery System Preferred Alternative. The approval
followed a Colorado Springs City Council vote in favor of a resolution
to formally recognize the commitments in the terms and conditions
of the Pueblo County 1041 land-use permit on April 14, 2009.
The permit identifies construction and environmental mitigation
required to build the SDS permit through Pueblo County as well as
outlining how the approach to acquiring property for the project.
Following is a high level summary of the conditions included in
the 1041 Permit. Colorado Springs, acting in the capacity of project
manager for SDS, will be required to:
Mitigation of Fountain Creek Impacts
| • |
Mitigate impacts to Fountain Creek from SDS
by funding $50 million to the new Fountain Creek Watershed,
Flood Control and Greenway District (District) or similar entity
for erosion, sedimentation, flood control or water quality improvement
projects. |
| • |
Payments would be made in five annual installments
after water begins flowing through the SDS pipeline. |
| • |
Of that total, Colorado Springs would pay
$300,000 in equal annual installments of $100,000 each beginning
July 1, 2009, to assist in the identification and prioritization
of projects, and to fund a study or studies of opportunities
for constructing flood control and sediment control facilities
which may include the feasibility of a dam or dams on Fountain
Creek or its tributaries in order to improve flood protection
for the Fountain Creek Basin. |
| • |
Colorado Springs Utilities to invest $75
million in planned improvements to its wastewater collection
system or reuse systems by Dec. 31, 2024 to protect against
future spills, increase its opportunities for reuse, and mitigate
possible water quality impacts from SDS. |
| • |
Reduce sediment load in lower Fountain Creek
prior to SDS construction by dredging and sediment-collection.
|
Stormwater Management
| • |
Maintain stormwater controls and other regulations
intended to ensure that Fountain Creek peak flows resulting
from new development served by the SDS project within the Fountain
Creek basin are no greater than existing conditions. This requirement
can only apply to Project Participants who have the legal authority
to regulate in this manner. |
Protection of the Arkansas River/Pueblo Reservoir
| • |
SDS participants would continue participation
in the Pueblo Flow Management Program to protect Arkansas River
flows below Pueblo Dam for recreation and the Arkansas River
Corridor Legacy Project. |
| • |
Colorado Springs Utilities to work with the
Pueblo Board of Water Works to outline how the two cities will
maintain a storage pool in Pueblo Reservoir to permit the release
of water into the Arkansas River during times when the flow
in the river could fall to dangerously low levels – at
or below 50 cubic feet per second (cfs). |
| • |
Wait to begin construction at or near Pueblo
Reservoir Dam until after the Bureau of Reclamation performs
its dam-safety review and accepts the design construction plans. |
| • |
Colorado Springs Utilities would voluntarily
participate in developing a management plan for Pueblo Reservoir
to protect reservoir levels and recreational opportunities on
Pueblo Reservoir to the extent feasible, when and if the Southeastern
Colorado Water Conservancy District, Reclamation and other affected
parties agree to develop such a plan. |
Other Water Users
| • |
Colorado Springs could elect to add SDS project
participants if the entities are located in El Paso and Teller
Counties within the Arkansas River Basin and agree to meet criteria
outlined in the conditions. |
Property Owners/Construction
| • |
Treat private property owners fairly, avoid
creating financial burdens for property owners, and use power
of eminent domain “only as a last resort” to acquire
property and easements. |
| • |
Mitigate construction impacts and restore
disturbed lands. |
| • |
Take “substantial steps” within
36 months to “construct the permitted development.” |
Details of the Pueblo County 1041 Permit Conditions
| • |
Final resolution approving the permit. [Link
to resolution] |
| • |
Terms and conditions. PDF
(47 KB) |
| • |
Permit Mitigation Appendix. PDF
(438KB) |
| • |
MOU Arkansas River Low Flow Program. PDF
(421KB) |
| • |
MOU Delivery of Municipal Water Supplies
from Pueblo Reservoir. PDF
(734KB) |
Articles and Presentations
| • |
SDS Factsheet. PDF
Document. |
| • |
April 22, 2009 – Pueblo County approves
Utilities secures key permit for SDS. Pueblo Chieftain article
on 1041 permit approval. PDF
Document. |
| • |
April 21, 2009 – Utilities secures
key permit for Southern Delivery System. Gazette article on
1041 permit approval. PDF
Document. |
| • |
April 9, 2009 – Presentation Colorado
Springs City Council on 1041 Permit conditions. PDF
Document. |
| • |
December 9, 2008 – Presentation to
Pueblo County Commission on 1041 Permit application. PDF
Document. |
|