|
UNEV will be an interstate common carrier Pipeline and will be
constructed and operated under oversight of the United States Department
of Transportation and Office of Pipeline Safety. Holly also follows
the regulations established by the Environmental Protection Agency,
and other federal and state regulatory agencies.
Holly has been working with the U.S. Bureau of Land Management,
the lead agency on the project, to look at alignment options and
construction considerations. The two entities will conduct extensive
environmental studies to comply with the National Environmental
Policy Act (NEPA) and various other federal, state and local environmental
regulations. As part of the process, stakeholders and the public
will have the opportunity to comment on the project. For more information
about the NEPA process or the public scoping meetings visit www.blm.gov/ut/st.
As long-time stewards of the environment and as good corporate
citizens, Holly is designing a construction process that takes into
account the special needs of various sections of the Pipeline. Holly
is working with the U.S. Bureau of Land Management to put in place
a Comprehensive Plan of Development.
The construction of the Pipeline for the most part will be the
conventional trenching process however in some areas a horizontal
directional drill or bore will be used to go under roads and waterways.
Holly will put in place a comprehensive plan to restore and revegetate
the area when finished.
Holly is taking much care to ensure UNEV will be constructed and
operated in a safe manner. The Pipeline will be constructed under
the stringent guidelines required by the U.S. Department of Transportation.
The 400-mile, buried UNEV Pipeline will be 12-inch diameter welded
steel. All pipe used will meet the industry’s standards set
by the American Petroleum Institute. Each weld will be x-rayed and
before going into service the entire Pipeline will be pressure tested
with water at a pressure that is at least 125 percent of the maximum
operating pressure.
The pipe will be continually coated using fusion-bonded epoxy or
another suitable coating as recommended for the soil conditions
to inhibit external corrosion. The Pipeline will also be under cathodic
protection, an electrical means to inhibit corrosion, which is a
secondary level of corrosion protection.
 |
| Bi-directional pipeline pig |
An internal inspection tool, called a smart pig, will be used to
measure metal loss due to corrosion or third-party damage on a periodic
basis. Corrosion coupons will be installed at each end of the Pipeline
to measure any corrosive activity. If required, corrosion inhibitor
chemicals will also be injected at the Pipeline’s origin.
Surface and aerial patrols will occur every other week or at least
26 times a year. These patrols will monitor for any third-party
encroachment, right-of-way condition and the condition of the line
markers and above ground valves.
Holly’s control center will monitor the flow and pressure
of the Pipeline 24 hours a day, seven days a week. If all communications
are loss for more than one minute the Pipeline will shut down. Holly
provides training to all local employees to perform the duties of
a first responder. The duties emphasize protection of the public
first followed by the protection of the environment.
|